WSP has an extensive portfolio comprising major clients all over the world
Luck explains , for every 1KWh entering the data centre , it would require 600w to remove the heat .
This saw an industry wide move away from this system , experimenting in water cooling and air cooling systems to bring consumption down and realise significant cost savings in the process .
“ There were a lot of new cooling systems coming into play ,” says
Luck . “ But there was a flaw . They had fixed set points that required a set temperature and system . This didn ’ t allow for any versatility of agility regarding external environmental factors .”
This is where WSP , through Luck and his Power Systems team , has developed what he feels to be a unique cooling solution , one that utilises fresh air cooling
www . businessrevieweurope . eu 117